From our database archive
These maps were leaked from the Israeli intelligence.
Messi Tax Plan 11\B
Expansion of the Dorad Power Station
Change to the 4/11 National Defense Program
Surface runoff management plan (drainage)
This is the secret places of the Iron Dome?
But the files in the matter that in some files there are encrypted sentences written in a strange way and this is what indicates the importance of this data.
We Stand With Truth
We Stand With Humanity
We Still Have More Surprises Soon
Expect Cyber Ghosts
It’s an open war with Israel
Arabian_Ghosts #OpIsrael
In honor of
Avi Goldschmid, Goldschmid – Editors of the review
Peace and blessings,
Subject: TATL 11B – Expansion of the Dorad Power Plant – Guidelines for an Environmental Impact Assessment
TATL 11B is a plan to expand the existing Dorad Power Plant in Ashkelon by constructing a combined cycle power plant adjacent to the existing plant.
The plant’s capacity will be approximately 650 megawatts on an area of approximately 5 dunams.
As part of the plan, the plant will be connected to the existing infrastructure systems at the Dorad plant, including the natural gas pipeline and the diesel pipeline. The station will also be connected to the electricity grid via an existing 400 kV line to the Dorad station.
These guidelines for the environmental impact assessment are a product that presents the full range of conflicts and solutions provided within the framework of the plan in order to prevent or minimize the impacts of the plan on the environment.
By virtue of my authority under Section 76C (4)(5) of the Planning and Building Law, 1965, the following guidelines are submitted
for the preparation of an environmental impact assessment for the National Infrastructure Plan (NIP) 11B, which was submitted to the Secretariat of the
National Committee for the Planning and Construction of National Infrastructures for the purpose of a preliminary planning review on
16.02.20
Sincerely,
Naama Ashur Ben-Ari


You must be logged in to post a comment.